Construction journal · September 21, 2026
The slab over the 1st floor is cast, masonry on the ground floor is under way
The structure of building C3 is advancing: the slab over the 1st floor has been cast and masonry works on the ground floor are under way. Photos from the site are published below and updated as the works progress.
What was done
- The slab over the 1st floor has been cast (photos from 8 September 2026).
- Masonry on the ground floor is under way.
- Works are carried out under building permit 422/10.11.2025.
What comes next
- Continuing the structural works on the upper levels.
- Handover of building C3 remains estimated for Q3 2027 (an estimated date, confirmed in the pre-contract).