Building C3
Construction progress
Follow the progress of the works. We update the progress and the photos from the construction site periodically.
- Overall progress
- under way
- Updated
- September 30, 2026
- Estimated completion
- Q3 2027
Permitting & site setup
CompletedBuilding permit AC 422/10.11.2025 obtained.
Structure & infrastructure
In progressSlab over the 1st floor cast; the structure continues on the upper levels.
Enclosures & partitioning
In progressMasonry on the ground floor under way.
Systems & finishes
UpcomingExterior works & handover
Upcoming
Construction journal
Latest update · September 21, 2026
The slab over the 1st floor is cast, masonry on the ground floor is under way
What was done
- The slab over the 1st floor has been cast (photos from 8 September 2026).
- Masonry on the ground floor is under way.
- Works are carried out under building permit 422/10.11.2025.
What comes next
- Continuing the structural works on the upper levels.
- Handover of building C3 remains estimated for Q3 2027 (an estimated date, confirmed in the pre-contract).
Photos from the construction site
Photos published on September 30, 2026
Photos published on September 21, 2026
Photos published on September 10, 2026
Zidărie Parter
Zidărie Parter
Placa peste etajul 1
Photos published on September 5, 2026
Photos published on August 20, 2026
Photos published on August 12, 2026
Photos published on August 11, 2026
Photos published on August 3, 2026
Photos published on July 30, 2026
Photos published on July 29, 2026
Photos published on July 27, 2026
FINALIZARE SÂMBURI PARTER
FINALIZARE SÂMBURI PARTER